|
||||||||
|
Paulinenaue: ICE rail link Hamburg-Berlin soon to be 230 km/h Paulinenaue - a site of superlatives After the abandonment of the project for the high-speed magnetic rail link between Hamburg and Berlin, the German Rail company, Deutsche Bahn AG, decided in favour of a second stage improvement of the existing track. Peak speeds of 230 km/h will reduce the journey time from Hamburg (Main Station) to Berlin (Zoo) to around 100 minutes. The whole project will cost 650 million euro. The shortened journey time is to be included in new timetables from the end of 2004. An earlier reconstruction at the end of the 90s had seen the speed for this line increased to 160 km/h. In terms of construction, the greatest challenges to be overcome were on a 14.5 km length between Paulinenaue and Friesack, which formed part of the Spandau-Neustadt section. The boggy ground there is capable of taking very little load. In the earlier construction stage, the rail embankment had been founded on 40,000 partially injected vibro columns (PIVC) and geogrid reinforcement. Full closure - and 76 days of round-the-clock working A consortium led by the engineering management of Wittfeld (Wallenhorst), H.F. Wiebe (Achim), Gebr. von der Wettern (Cologne), Ludwig Freytag (Oldenburg) and Matthäi (Verden) was awarded the contract for the section and formed the joint venture company "ABS Hamburg-Berlin, PRA 1".
During the planning phase, DB Projektbau GmbH was at first in favour of a partial closure with single track operation, as had been adopted in other sections. In order to ensure that this demanding and high quality project was executed in the best possible manner, a decision in favour of a specified period of full closure was made in consultation with the joint venture partners. Exactly 76 days were allowed for this to take place in summer 2003. Several sites on the section running in parallel
Work on the section started simultaneously at several sites. First the existing track bed, along with the associated groundworks was completely removed. The original boggy ground was then replaced to the level of the groundwater table. Approximately 1 metre of the partially injected vibro columns forming the piled foundations was then exposed and cut off to existing ground level. Their condition was recorded and repairs carried out where necessary.
The 14-metre wide rolls of geogrid were placed transversely to the track and overlapped by one metre. Each layer of geogrid was precisely installed to laser accuracy and tolerances of less than 10mm, in accordance with the manufacturer's recommendations. HUESKER manufactured the custom-made geogrid in 210-metre long rolls. The Supersite in figures
Fig. 1: Three layers of Fortrac® geogrid from HUESKER Synthetic reinforce the embankment on the Paulinenaue - Friesack section, ensuring that the high speed ICE train arrives on time. Typical cross section: Wittfeld, Wallenhorst
Fig. 2: The figure shows the construction of the new embankment on the Paulinenaue section. Three layers of PVA Fortrac® geogrid type R 200/200-30 M were placed at 300mm vertical spacings. Das Unternehmen HUESKER Synthetic GmbH, Gescher Building with geosynthetics - all around the globe! HUESKER Synthetic GmbH, Gescher designs, manufactures and markets custom-made geosynthetics for the construction industry as well as technical textiles for agriculture, industry and business. The product portfolio offered by HUESKER Synthetic GmbH is as diverse as its applications. Standard products include synthetic fabrics, geogrids, composites and clay liners. Nonwovens, drainage and erosion protection mats, synthetic membranes complete the range. A few examples: Fortrac® is a flexible, extremely high strength geogrid with a proven successful record in reinforced soil - HaTelit® is a flexible asphalt reinforcing grid - Fornit® is a biaxial geogrid for base and subbase reinforcement of roadways - Comtrac® is a high modulus reinforcement material that can also be combined with various nonwovens - Stabilenka® is a high quality, permeable fabric that can be used for embankment stabilisation. Incomat® is a high strength fabric formwork for slope and bed protection. HaTe® filter nonwovens and fabrics are suitable for separation, filtering and stabilisation. They are used in the maintenance of waterways, for example as bank protection. The geosynthetic clay liner NaBento® - a composite with bentonite as the sandwich filling - finds application in hydraulic structures and environmental protection. With Ringtrac® tube fabrics, geotextile encased sand columns (GEC) can be constructed offering an economic alternative foundation system for embankments on soft soil with controlled low settlements In over 40 years of close cooperation with its customers, consultant engineers, research institutions and testing laboratories, HUESKER has developed individual solutions for various engineering applications in addition to the standard product range - well thought out, innovative, economic and environmentally friendly. HUESKER can provide comprehensive construction solutions over a wide range of applications; from soil and foundations, roads, rail and airports, right up to hydraulic structures, waste disposal, industrial and polluted land reclamation and reinforced asphalt surfacing.
|