Until now, whenever bridge building was being designed, the traditional approach for a
bridge support was to consider a concrete abutment wall or a cast-in-situ bored piled
foundation. A project in Ilsenburg, Germany, has shown there is a comparable option to
the conventional form of construction, namely Geosynthetic Reinforced Soil (GRS).
The starting point was the tender issued by the Wernigerode local authority covering
the construction of a replacement bridge over the River Ilse as part of the upgrading
of the K1355 district road at Ilsenburg. The authority's proposal intended the bridge
to be supported on bored piles. In addition, the abutment was designed as an anchored
gabion structure incorporating the piled elements.
The proposal from consulting engineers IBH - Herold & Partner Ingenieure, Weimar,
acting for contractor Matthäi, Magdeburg, was to construct the abutment as a GRS structure.
The design would dispense with bored piles, making it Germany's first permanent bridge
abutment to be constructed using GRS - built with HUESKER's Fortrac® geogrid; planned
and designed by IBH - Herold & Partner Ingenieure.
In place of load transfer through the piles, this proposal involves load transfer onto
the GRS structure, onto which the abutment bearing shelf is directly cast. This structure
comprises layers of fill placed and compacted onto Fortrac® geogrid.
The front face is constructed from galvanised steel gabion baskets filled with crushed stone.
The geogrid is double-looped around the steel facing and turned back. The reinforcement material
- Fortrac® geogrid type R140/30-30MP made from PVA, is cost-effective, has excellent structural
engineering properties and fulfils two important requirements. First of all, PVA geogrid has
excellent long-term durability with a working life of 120 years, even when placed in a high pH
fill, in this instance pH 10 -11. Secondly, the geogrid has an extension under working load
of much less than 6 % and so is particularly suited to this situation, where only a very low
deformation can be tolerated. A further advantage of Fortrac® geogrid is its flexibility in
all weather conditions, making installation work simple and cost-effective.
The GRS construction method offers several advantages enabling the work to progress rapidly
and above all with cost benefits. The sequence of operations in the construction of the GRS
abutment is quite simple, leading to a substantial shortening of the construction period.
In addition, there is no requirement for dewatering, sheet piling or shuttering and concrete
curing time is eliminated.
Compared with the client's scheme, the GRS solution offered around 30 percent saving - and
was half the price of a conventional reinforced concrete substructure. There are similar
savings in construction time; 25 percent reduction opposite the client's scheme and 70 percent
compared with the reinforced concrete version.
On the question of stability GRS is subject to structural calculations and certification.
External and internal stabilities require a check according to EBGEO /3. The stability check
on the Wernigerode bridge abutment proved to be excellent.
But that is not all. As this bridge was the first of its kind, a vertical inclinometer was
installed at each abutment, which would allow the horizontal movements in the GRS structure
to be accurately recorded. Settlement measurement points were set up on the bearing shelf
to enable surveys of the vertical movement of the structure to be carried out.
DBut that is not all. As this bridge was the first of its kind, a vertical inclinometer was
installed at each abutment, which would allow the horizontal movements in the GRS structure
to be accurately recorded. Settlement measurement points were set up on the bearing shelf
to enable surveys of the vertical movement of the structure to be carried out.
The abutment was completed in October 2000 and opened for traffic in December 2000. So
far the measured vertical deformation is 4 - 8 mm and horizontally in the
order of 1 - 2 mm.
The use of Fortrac® geogrid also makes structures more flexible than the comparable
traditional construction method, which means that cracks, caused by deformation or
movement in a stiff concrete structure, are less likely.
This project represents a true innovation in bridge construction in Germany; a time-saving
and cost-reducing solution, offering recycling potential and environmental benefits.
Thanks to Fortrac® geogrid from HUESKER - every bit as good as the traditional design.
Photo: HUESKER / D-Gescher

Fig. 1: BU Foto Brückenwiderlager KBE-Bauweise:
K 1355 district road bridge over the River Ilse at Ilsenburg - the first permanent geogrid-reinforced bridge abutment in Germany

Fig. 2: BU Foto Brückenwiderlager Gabionenkörbe:
Load transfer takes place through the GRS structure, onto which the abutment bearing shelf is directly cast.
The facing section is constructed from galvanised gabion baskets, filled with crushed stone.
Grafic: HUESKER / D-Gescher

BU Brückenwiderlager Querschnitt:
Cross section: Germany's first permanent bridge abutment, constructed at Ilsenburg, using a GRS design and Fortrac® geogrid
|