Huesker Fortrac® polyester geogrids have been used to control differential
settlement as part of the design and construction of the approach embankments to
the new Welham road bridge on a newly aligned section of the A614 near Goole in
East Yorkshire.
Under the ECC target cost contract, Mowlem Northern Civil Engineering was
responsible for the design of the scheme which included value engineering during
the design process. The client, East Riding of Yorkshire Council, had specified
very tight limits on the allowable surface and differential settlement on the
bridge structure and approach embankments.
The ground conditions in the immediate vicinity of the river consisted of five
metres of peat and between one and two metres of soft silts and sands overlaying
two to three metres of firm laminated clays. Sands and gravels, with mudstone,
underly these superficial deposits at approximately twelve metres below existing
ground level.
Due to the tight serviceability criteria and poor ground conditions, Mowlem,
along with their designer Pell Frischmann, opted for a piled solution very early
on in the design process. As Huesker geogrids had been used successfully on the
recently opened A63 Selby Bypass, just fifteen kms west of the Welham bridge scheme,
Graham Horgan, Huesker's northern application engineer, was asked for advice
prior to detailed design commencing.
Construction Techniques
The embankment was constructed using driven cast in-situ, (DCIS), piles with
flared heads to depths of between twelve and thirteen metres. The core of the main
embankment was designed using PFA fill with a mine stone shoulder. These
lightweight locally available fills reduced the loadings on the piles allowing
the pile spacings to be optimised.
The original indicative design was based on a square pile arrangement with a reduced
pile spacing beneath the bank seats and the geosynthetic reinforcement design based on
the British Standard BS8006 approach. This approach details two orthogonal layers of
high strength reinforcement. However, increasing the pile spacings slightly along
the length of the embankment and decreasing the spacings across the embankment enabled
the same grade of geosynthetic reinforcement, Fortrac® R800,
to be used in both directions.
Huesker provided this reinforcement in custom made lengths to eliminate wastage and reduce
handling on site. In addition, they were produced and delivered in five weeks so as not to
affect the tight construction programme.
Limiting Differential Settlement
The longitudinal geosynthetic reinforcement was also extended thirty metres into the
transition zone beneath the traditional embankments, beyond the first and last piles.
Not only did this provide anchorage but, additionally, it helped to limit the potential
for differential settlement between piled and un-piled embankments.
The PFA fill, which tends to exhibit a pozzolanic reaction, was omitted from the zone
immediately above the edge piles and replaced with a granular wedge of a more dilatant
fill. This also helped to compensate for differential settlements at the base
of the embankment.
In addition, loose compressible soil was placed between the first six rows of piles
at the low ends of the embankment to encourage the geosynthetic reinforcement to
develop its tension whilst placing the first few layers of overlying embankment fill.
This technique was originally used on the Bingley By-Pass to assist in reducing any
surface undulations on thin embankments.
Improved Alignment
The 40 week design & construct contract for the A614 realignment was awarded to Mowlem
Northern Civil Engineering in December last year and forms part of Mowlem's three year
framework agreement with the East Riding of Yorkshire Council.
The scheme involved the construction of a new one km section of 9.3metre wide carriageway
and a new bridge over the River Foulness. The existing bridge had been assessed as inadequate
in previous inspections and a "temporary" bailey bridge installed to alleviate traffic loadings.
As the bridge was on a relatively tight bend in the road, the decision was taken to build
the new bridge on a new improved alignment with the old road being maintained to provide
access to local farms.
The bridge and new road alignment opened to traffic on 1st October 2004.
Photo: HUESKER Synthetic / D-Gescher

Fig. 1: Fortrac® 800, (foreground) longitudinal reinforcement installed, (background) River Foulness in Flood

Fig. 2: The completed pile supported, reinforced soil, bridge abutments
Grafic: HUESKER Synthetic / D-Gescher

|